Update, Blackrock Harbour and Village Renewal Project, April 2016

    In response to a recent question to the Chief Executive of Cork City Council by Cllr Kieran McCarthy for an update on the current work programme of the Blackrock Harbour and Village Renewal Project, a report was issued. The construction period for phase 1 has commenced, comprises 43 weeks and the project should be substantially completed in January 2017. This will consist of the realignment and widening of Convent Road, Blackrock Road and the Marina including boundaries, footpaths, surfaces, crossing and underground utility works common to phases 1 and 2. The scope of work will be limited to the current level of available funding. Further efforts will be made this year to secure the remaining funding so that work on phase 2 can commence at an early date. Funding applications have been made to a number of agencies including the Department of Agriculture, Food and the Marine, the National Transport Authority and the South East Regional Authority. Unfortunately, however these applications have not been successful. In the absence of additional funding, the Council proposes to split the tendered works into phases and to proceed with that portion of the works that can be executed. Commenting, Cllr McCarthy noted: “this has been a long, difficult and frustrating process of planning work over two decades. It’s a testament to the tenacity, patience and good will of Blackrock residents who have pushed and pushed to make this current construction phase happen”.