Cllr McCarthy: Douglas Flood Relief Scheme on track for October 2020 Completion.

Press Release: 17 June 2020

Independent Cllr Kieran McCarthy has welcomed that the Douglas Flood Relief Scheme is on track in its schedule to be finished this October. The works are being carried out in five separate areas – St Patrick’s Mills, Douglas Community Park, Ravensdale, Ballybrack Woods & Donnybrook Commercial Centre. A report this week from Cork City Council, who are working with the OPW, outlines that the works at St Patrick’s Mills are fully complete. The works and Ballybrack Woods are 99% complete apart from the installation of surface dressing to the maintenance access road. The works through the Community Park are progressing well with the construction of flood embankments, footpaths, gym equipment area and public realm works under way at present.

The works in the community park are currently programmed to be completed at the end of October 2020, but the project team are hoping that this works area can be progressed ahead of schedule. The works through Lower Ravensdale are underway with the installation of sheet piled walls and the installation of the new Church Road culvert, outside Douglas Community Park. Access to Westbrook Gardens will be maintained from Douglas West. Access to the Community Centre and Ravensdale is maintained from the East of Church Road. The associated closure of Church Road is scheduled to be lifted on the 03 July 2020, but may require an extension of time.

Cllr McCarthy noted that much of his correspondence from constituents are serious worries about the cutting down of trees around Church Road; “the programme of works places emphasis on the replacement of trees as well as improving the connectivity and pedestrian routeway from Ballybrack Woods across to Douglas Community Park. In the Community Park, the Contractor cut down less trees than was originally outlined in the public consultation process in the past two years. Trees will be replaced on a one-to-one basis. They will not be as mature as the originals but re-planting will be done with trees that have a 200-250mm girth trunk, which depending on the tree type would be three to five metres tall. The one-to-one replacement ratio in the area along Church Road may not be achieved as the area will have a large paving plaza across Church Road and the river has been widened, but there will be new trees re-planted there. I am watching progress carefully and getting updates from engineers. There is a project website for Douglas (including Togher Works) Flood Relief Scheme at www.floodinfo.ie/frs/en/douglas/home/, which has drawings and photograph montages on what the end product will look like”.